What type of damages is requested by the OWNER for delays in project completion?

  1. Punitive damages

  2. Regular damages

  3. Liquidated damages

  4. Exemplary damages

The correct answer is: Liquidated damages

The correct answer, liquidated damages, refers to a specific form of compensation that is predetermined and stipulated in a contract. These damages are typically agreed upon by both parties at the time of contract formation, specifically to address potential delays in project completion. The purpose of liquidated damages is to provide a clear and enforceable remedy in the event that the project does not meet its timeline, thus protecting the OWNER from the financial implications of delays. Liquidated damages help to establish a mutual understanding regarding the importance of timely completion and help to mitigate disputes about the extent of damages incurred due to delays. This contrasts with punitive damages, which are intended to punish wrongful conduct and are not applicable in the context of delays. Regular damages may not specify amounts in advance and exemplify the damages actually suffered, which could lead to uncertainty. Exemplary damages, similar to punitive damages, also serve a different purpose by seeking to deter future misconduct rather than compensating for agreed-upon delays. Thus, liquidated damages serve as the most appropriate and effective means to address the OWNER's interests in the event of project completion delays.