Ace the Architect Adventure 2026 – Build Your Way to Success with Our Pro Practice Test!

Question: 1 / 400

If the Owner wants to adjust the estimated cost after awarding the contract to a winning bidder, what should he consider doing?

Change Order

A change order is the correct approach when the owner intends to adjust the estimated cost after a contract has been awarded. A change order formally modifies the original contract to reflect changes in scope, drawings, specifications, or other contract documents, which may occur after the bidding process. This process is essential as it ensures that the contractor is compensated for additional work or changes required by the owner while maintaining the project's integrity.

Utilizing a change order promotes clear documentation and tracking of changes, which is critical in construction projects to avoid misunderstandings and disputes. It also enables the owner to incorporate necessary adjustments within the established contractual framework.

The other options, while they might seem reasonable in various contexts, do not directly address the process of adjusting costs after a contract has been awarded. Revising the scope could lead to a change order, but it is not the actual mechanism for cost adjustment. Changing the architect might complicate or delay the project unnecessarily and does not directly facilitate a cost adjustment. Negotiating with the contractor could be a route for unforeseen circumstances but is less formal than issuing a change order and might lead to misunderstandings regarding the contractual terms.

Get further explanation with Examzify DeepDiveBeta

Revise scope of works

Change Architect

Negotiate with the Contractor

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy